The district heating system of Brasov has gone through several transformations in the attempt to find a solution for the zones located within the urban agglomeration of Brașov. Unfortunately, the lack of vision and the misunderstanding of the advantages of such a system, coupled with a legislation that allows for easily installing natural gas individual boilers, led to a situation where only 4% of the local population was still connected to the DH in 2014 (reference year of the project).
The future of this system is directly linked to the local policies, which should be supported by the population, by the real estate developers and last but not least, by policy makers.
The current strategy is trying to provide insight into the renewable sources that could be used in the future in order to ensure energy security and cost efficient heat supply at local level.
The current overall targets of the Brașov municipality have been developed in the Sustainable Energy Action Plan (SEAP) for 2010-2020 (2008 as reference year), developed as part of the Covenant of Mayors, which is full part of the strategic political documents for the sustainable development of the city. The general objectives for 2020 are:
Regarding the policy measures, the municipal buildings are being submitted to an advanced process of energy upgrading and are permanently monitored (monthly) by the ABMEE (local energy agency), who annually develop an energy performance report for all pre-university educational institutions, based on which the municipality prepares its investment plan. From 2017, ABMEE has been acting as the community energy manager.
The DH system is split into 4 areas and each area is using a mix of energy sources like natural gas heat boilers and the heat purchased from an external company. The purchased heat is generated from highly-efficient cogeneration plants using natural gas, part of the DH system.
The reference scenario reflects a development where no certain additional action will be undertaken and the current supply situation will persist within the considered time horizon. The heat for the main district heating networks will be purchased from the private company producing heat in highly-efficient natural gas-fired cogeneration engines and heat only boilers at a certain price expected for the investigated time horizon. Investments will be made to replace 50 % of the old parts of the network (not renewed within the last 10 years).
In the alternative scenario there will be networks optimization to cut down the losses in each of the district heating systems to 20% of annual produced heat. Also 50% of the not yet renewed networks will be renewed within the considered time horizon to be able to connect additional consumers. Additionally, the public local service will install own production units (A small biomass boiler, solar thermal panels plus heat storage, a heat pump and also refurbishment of district heating plants (transforming substations to district heating plants) in the different parts of the district heating system to bring supply closer to the final consumers. Additional needed heat will be purchased from the private company, part of Brașov DH system. In order to enable the transformation of the heating and cooling sector of the city of Brașov, a quantitative assessment of the following selected policies has been performed: long term loans for DH infrastructure, support of connection to DH network, CO2 tax, subsidies for RES technologies in DH, zoning.
The quantitative assessment showed that single policies are not enough to tackle all problems district heating faces in Brașov. It is necessary to combine different policies to ensure a modernization of the DH systems and to bring back confidence and the required consumers, the complex package of local policies being: