As European cities accelerate their climate transitions, a critical question arises: how can municipalities work with private partners to put climate at the heart of their agenda as well?
In Ghent, private developers made climate transition the core of their work. Indeed, as Ghent’s former industrial port has become De Nieuwe Dokken, the private developers decided that in the brand-new district neighbours would share more than just a street. Today, through the DuCoop cooperative, the community pools heat, EV charging, and energy storage.
At the heart of the De Nieuwe Dokken project is DuCoop, a multi-service cooperative that runs the neighbourhood’s heating system, as well as the electric vehicle (EV) charging points.
The system is powered by a mix of technologies designed for circularity. It recovers residual heat from neighbouring industries (Christeyns and Govi) and uses solar PVsv to generate electricity for the EV charging. A shared battery stores surplus power, flattening demand peaks and offering local flexibility to the wider grid. Residents gain access to district heating and shared EV charging as part of their real estate ownership, becoming cooperative members automatically.
While the project initially experimented with on-site wastewater treatment recovering heat, the model has now evolved. Indeed, the on-site treatment plant ceased operations in July 2026, but the lessons learned have informed future phases.
The success of DuCoop was not accidental; it was engineered by the Municipality of Ghent. In 2013, the city established a Climate Transition Taskforce to make climate action a cross-cutting priority. When the city identified the potential for wastewater heat recovery, it realized existing utilities were not yet ready to pilot the technology.
Rather than waiting, the city turned to the De Nieuwe Dokken redevelopment, where the heating network had not yet been designed. Through its development agency, Sogent, the municipality commissioned a feasibility study on heat recovery potential to the tender documents.
The winning bidder, Schipperskaai Development, partnered with Clean Energy Innovative Projects (CEIP) and decided not only to integrate heat recovery in their proposal, but to launch DuCoop to manage it collectively with all the stakeholders involved.
The Ghent experience offers two critical lessons for other municipalities looking to replicate such models:
The De Nieuwe Dokken project illustrates that anchoring climate goals in corporate agendas is not only possible, but that sometimes businesses go even further. By building partnerships with all the stakeholders involved, DuCoop is successfully managing an experimental heating system with a locally built cooperative system.
Find the full Ghent case study and more inspiring examples on the Homegrown Energy Campaign

This information campaign is ran by Energy Cities together with the EU Covenant of Mayors. Each month, we bring new stories and fresh angles on how local municipal teams manage to overcome concrete obstacles to create hyper-local, community-anchored energy services that create long-term benefits for the area.